Yahoo Answers is shutting down on 4 May 2021 (Eastern Time) and the Yahoo Answers website is now in read-only mode. There will be no changes to other Yahoo properties or services, or your Yahoo account. You can find more information about the Yahoo Answers shutdown and how to download your data on this help page.

how does the critical path impact how you manage the project?

1 Answer

Relevance
  • Anonymous
    1 decade ago
    Favourite answer

    critical path gives u the least time required to complete your project.it means that the activities which are on the critical path should be carefully monitored any delay in these critical activities will lead to an equivalent delay in total project time.

    slack is zero for critical activities.

    knowing the critical path helps to crash the project. that is u reduce the project completion time with least utilization of resources.